We are definitely moving into the "remodel" aspect and out of the "demo" phase! Very exciting!!
This week the electrical work has been completed, and our circuit box is now on the outside of the house instead of in the back guest room.



 The circuits in the panel will be labelled when all the electrical work is finished.

The rest of the old flooring is out and there is new plywood in preparation for the bamboo flooring to come.

 Front bedroom from pocket door entrance.




The sheet rockers came today and got all the walls done. Tomorrow they'll tape, then begin applying the mud and texturing.

 Back bedroom

 Front bedroom, minus a doorway!

 Back hallway from the garage.